FSD-FRM-03 — Service Acceptance Record

FitSDTier 4draft

Service Acceptance asks: is it proven done? Walk each Service Acceptance Criterion and record the evidence. A solution is accepted into service only when each is met and evidenced, not merely configured. The approaches were designed at Gate 2 (FSD-FRM-02); here they are proven. Record failed attempts and known thinness alongside the pass — a successor reads this table before anything else. (Terms: see FitSD — Definitions.) The live copy is held in the team’s work-tracking system; this is the blank template.

FieldEntry
Solution title
Solution Owner
Delivery project (ref)
Linked Gate 2 (FSD-FRM-02)
Date

For each criterion, record the evidence (a link, a date, a reference) and whether it meets your organisation’s standing SAC baseline. The criteria are defined once in FitSD — Service Acceptance Criteria; below is what proof looks like at acceptance. Where the baseline’s applicability rules say a criterion doesn’t apply to this service, record N/A per baseline with the reason, a recorded call, not a skip.

CriterionEvidence / linkMet? (Y / N / N/A per baseline)
Documentation: HLD (carrying the design decisions and rationale), runbook, recovery procedure, operating procedures (SOPs), user/how-to published
Backup (tested): backup in place and test restore performed, dated
Security: hardening applied, patch path set (FSD-RR), vuln posture acceptable, exceptions logged (FSD-SA)
Access: access model implemented; least privilege; JML handling confirmed
Availability: SLO met or accepted; capacity & scaling understood; DR position recorded
Monitoring & alerting: monitoring live; thresholds set; test alert observed end-to-end
Incident profile: service-level incident triggers & severities registered with the incident-management process (registration evidenced: accepted by whom, when)
Supportability / handover: support model agreed; runbook & SOPs accepted by the named operators — first line included — in a dated record; knowledge transfer / cross-training done; team ready; continuity assured (not reliant on one person); any new/changed standing procedure the service forced (Gate 2 §4) written & adopted
Cost / licensing: licences in place; ongoing run-cost (cash and operating effort) confirmed and owned

2. Conditions from Gate 2 — position at acceptance

Section titled “2. Conditions from Gate 2 — position at acceptance”

Each condition the Gate 2 sign-off attached, and how it stands now.

Gate 2 conditionPosition at acceptance

3. Outstanding remediation and open actions

Section titled “3. Outstanding remediation and open actions”

List any criterion not yet met (the record is re-presented when these are closed), and any open actions that don’t block acceptance — acceptance conditions land here too, each with an owner and target date, tracked until closed.

Criterion / actionBlocks acceptance? (Y/N)Action requiredOwnerTarget date

Acceptance names the live Service Owner on the service register (FSD-GV-2). Conditions carried with acceptance each have an owner and a target date (§3) and stay on the review agenda until closed.

FieldEntry
DecisionAccepted into service / Remediation required
Service register entryService, live Service Owner (and deputy, if your continuity rule names one), status
Approver
Conditions
Date